GMC South Wharf Substation — Full EPC

Direct-contract full-EPC delivery of the South Wharf substation for General Milling Corporation in Lapu-Lapu — an ongoing NCPSI project.

August 29, 2026
GMC South Wharf Substation — Full EPC

Overview

NCPSI is delivering the full engineering, procurement, and construction (EPC) of the South Wharf Substation for General Milling Corporation (GMC) in Pajo, Lapu-Lapu City — a direct-contract EPC project covering the substation's power house, distribution lines, and supporting electrical infrastructure.

Scope of works

  • Engineering design and procurement of major electrical equipment
  • Construction of the power house and 1.8 kV primary lines
  • Panel boards, automatic transfer switch, cable ducting, cable trenches, and cable trays
  • Grounding and lightning protection systems
  • Construction of secondary distribution lines

Project ongoing — targeted completion September 2026.

Client
General Milling Corporation (GMC)

Project Details

Client / Owner
General Milling Corporation (GMC)
Role
Full EPC — engineering, procurement, and construction (direct contract)
Location
Pajo, Lapu-Lapu City, Cebu
Contract Value
₱17,160,000
Timeline
Started May 2026
Status
Ongoing — target completion September 2026
Service Category
Substation EPC